The seven-span,
four-lane, precast prestressed voided slab bridge is 460 ft long
with a typical span of 67.5 ft. The 4 ft precast voided slabs were
erected using 100 ton crane. The adjacent decked beams were joined
together with a key mortar joints. Cast-in-place concrete topping
was used and as a result tie rods were not used on this project.
The structure is supported on twelve-150 ton circular driven
concrete pile extensions per bent.
Fourteen-foot
wide raised median was installed on Thunder Valley Sunset Bridge
as part of this project. The project includes the installation of
a 16-inch water line on brackets at edge beam with inserts.
 
Year
completed: 2006
Cost: 5,000,000
Contractor: Perini
Owner: County of Sacramento
The design challenges included: The voided slabs were joint together with
cast-in-place concrete
closure pour with interlocking reinforcing bars and strands above the invert cap. Environmental and Hydraulic issues.
Agencies: MRO Engineer, Placer County,
Perini, DMJM
References
|
Curt Carlson
Perinini Building Company
3655 Cincinnati Avenue
Rocklin, CA 95765
(916) 435-3300 |
|