ADKO Engineering provided Preliminary Engineering and Design of Deer
Lake Drive and Valley Green Pedestrian Bridges. ADKO’s portion
of the project included sound walls, transparent walls and
retaining walls for this South Sacramento Phase 2 project.
The South Corridor is approximately 4.80 miles and connects Meadowview
Station with Consumes River College. The corridor is planned as
a Light Rail Transit corridor. The 20,000 feet masonry block
will meet the noise requirements level. The environmental study
noise level requirements dictated the use of sound walls next to
adjacent communities. The 8,000 feet retaining walls were
required to minimize the right of way requirements.
The two Pedestrian Bridges in this corridor, Deer Lake Drive Bridge and
Valley Green Bridge, consist of structural steel single span
bridges that convey the 100 year design flow for Union House
Creek and provide access for pedestrians to Franklin Blvd and
Center Parkway Stations from adjacent communities. The
pedestrian bridges are 10’-0”wide and supported on seat type
abutments.

|